After you put the order to us, We offer you the production plan. Normally the machine drawings needs 2-3 weeks to be finished, We will inform you while the machines drawings are ready. And give you the report every 2 weeks when the machine ready at 20%, and We will offer you the production report every week when the machine ready at 50%, then We offer you the finished products sample pictures and the videos at 80%, We will invite you or your representative here in China come to inspect the machine when the machine is ready at 95%, after the inspection, We will make the subtle adjustment and the repainting and ready for shipping at 100%.